Week 3

As we approach the end of the third week of our track rebuild it's amazing the amount of work Clark and Kent Construction have got through.

The site has really started to look like a track as the 100mm (depth) of surface gets deposited and compacted.

By this time next week if all goes to plan the remainder of the track will be surfaced and the tarmac put down in the turns.

The hard graft doesn't end there however, the start hill and gate need to be commissioned next, followed by drainage and landscaping work. We're all starting to get a little excited though!